Installation Guidelines for
Septic & Holding Tanks
Site Conditions:
Site selection should consider ease of installation, in addition to
other factors. The installation site must be accessible to large,
heavy trucks weighing up to 40 tonnes. The construction area should
be free of trees, branches, wires, or parts of buildings which could
interfere with the delivery and installation of the concrete structure.
Most trucks will need to get within 0.91M (3ft) to 2.44M (8ft) of
the excavation to be unloaded.
Excavation:
Prior to excavation, all buried utilities should be located. Excavations
should be made with a moderate clearance around the installed tank.
More space should be provided as needed if other work than installation
is required. Excavations should be sloped as needed to comply with
construction safety requirements. Excavated materials should be stockpiled
a sufficient distance from the excavation so as not to impair the
movement of installation equipment.
Bedding:
Proper use of bedding material is very important to ensure a long
service life of an onsite septic system. Bedding material should be
provided on a site specific basis to yield a uniform bearing surface
and to ensure that the structure will not be subject to adverse settlement.
In most cases, a bedding of 150mm (6"") of 20mm to 25mm
(3/4" to 1") clean stone is sufficient. After placing the
stone, it must be leveled with special attention that there are no
large stones or rocks that could cause pressure points under the bottom
of the installed tank. Sites with silty soils, high water tables or
other "poor" bearing characteristics must have specially
designed beddings or bearing surfaces. In the event of excess excavation,
any backfill to be replaced must be adequately compacted.
Joint Seals:
Care must be taken with joint seals on concrete structures. High quality
preformed joint seals must be placed on carefully cleaned surfaces.
Seals shall meet minimum compression and other installation requirements
as prescribed by the seal manufacturer. Tank sections sealed on site
should not be backfilled until the sealant has settled.
Backfilling:
When backfilling, native materials can be used provided there are
no large rocks or stones placed against the tank. Equipment used to
backfill should not place their weight beyond the edges of the excavation.
While concrete tanks are heavy, they can float if the water level
in the hole is allowed to rise to a high level. Floatation can be
prevented by placing soil on top of the tank. In colder climates,
it is recommended that tanks be insulated before backfilling. In a
septic system, cold temperatures decrease the microbial action within
the tank, reducing waste treatment. Tanks which are unused for periods
of time can freeze, causing the tank to break. |